Norwin Campus Paving Project » Paving Project Closures & Updates

Paving Project Closures & Updates

Paving Project Updates
Closures & Updates:
 
  • July 22, 2024: Effective TUESDAY, JULY 23, Billott Ave from the VFW to the High School Baseball Field will be OPEN. Access will continue around the back of the High School. 
    • Until further notice, Mockingbird Drive will be closed between Norwin Middle School through the Main Campus to the High School Baseball Field.
    • Accessible entrances to the High School Campus include McMahon Drive to the Administration Building, and the S-Curve to the High School.
  • July 3, 2024: Effective MONDAY, JULY 8th (until further notice), the MAIN PARKING LOT in front of Norwin Knights Stadium/Administration Building is CLOSED as they will begin milling and paving this area. It is likely that this area will remain closed for the remainder of the summer. 
    • Access to the STADIUM/FIELD HOUSE:  If your group is utilizing the stadium, please park and enter/exit on the MIDDLE SCHOOL side of the stadium. The gates/ramps on the press box side of the stadium will be closed. 
    • Access to the TENNIS COURTS:  If your group is utilizing the tennis courts, please park at the MIDDLE SCHOOL and then walk down to the tennis courts. 
    • Access to the HIGH SCHOOL gymnasiums/pool/auditorium: If your group is utilizing the gymnasium/pool/auditorium, please park and enter/exit DOOR #6, the auditorium entrance/exit.  
  • June 26, 2024: Beginning Monday, July 1 entrances to the district campus from Entry Rd. and Billot Ave be closed until further notice. 
  • June 17, 2024: Beginning Tuesday, June 17 Billott Ave from the VFW to the High School will be OPEN. Entry Road from Hahntown Elementary to the High School will remain closed until further notice. 
  • June 4, 2024: Beginning Wednesday, June 5 Billott Ave from the VFW to the High School and Entry Road from Hahntown Elementary to the High School will be closed until further notice. 
 
It is encouraged to periodically check this page for the most up-to-date information on closures, delays, and updates. 
Tentative Paving Project Schedule*
*these dates are subject to change and will be updated accordingly 
 
Task Start Date Finish Date
Phase 1: Milling/Paving Friday, May 31 Monday, June 3
Phase 2: Sealcoat/Electric Tuesday, June 4 Wednesday, June 5
Phase 3: Milling/Paving Thursday, June 6 Friday, June 14
Phase 4 Saturday, June 15 Thursday, July 4
Phase 5: Milling/Paving/Electric  Friday, July 5 Tuesday, July 23
Phase 6: Milling/Paving/Electric Wednesday, July 24 Monday, August 5
Phase 7: Milling/Paving Tuesday, August 6 Monday, September 2
 
Please refer to the color-coded map below for the specific location of each phase. 
Paving Project Plan